Although the rain early this week slowed some of the construction activities on the project, the concrete
crew was still able to begin constructing the curb and gutter on Phases 2 and 3 starting yesterday. Ottertail
Aggregate has been the busiest subcontractor in town over the course of the week, with boulevard grading
occurring east of Third Avenue East behind the curb and out to 11th Avenue East where the new sidewalk
was constructed in May.
On Phases 2 and 3, Ottertail Aggregate has finished the subgrade preparation and hauled in the first half of
the aggregate base for the new roadway. Grading of the aggregate will be continuing over the course of
the next week in advance of the new pavement surface.
On Thursday, Knife Lake Concrete arrived in town and started with the construction of the new curb and
gutter from the west side of the intersection of Fourth Avenue West toward the intersection of County 34
and 51. Today, they will be completing the last of the curb and gutter on the phase, making connections of
curb near the new storm sewer inlets previously installed by R.L. Larson.
Next week Knife Lake Concrete will be returning to the site to begin construction of concrete flatwork
(sidewalk and driveways) throughout Phases 2 and 3. If you are affected by the construction of the new
concrete, please work with the contractor to stay off the new driveways and walks to allow for proper
curing of the new concrete.
In addition to Knife Lake working on the concrete in the phase, Ottertail Aggregate will be hauling
additional aggregate base throughout the phase to prepare the roadway for bituminous pavement.
Currently, dependent on weather conditions and upcoming rain, the plan is to pave the roadway the first
days of July, in advance of the Fourth of July.
If you have any questions, or want additional information on the project, the Perham Chamber of
Commerce has created a webpage dedicated to the project, which can be accessed at this link
(https://www.perham.com/2024msrp/). For more specific questions, feel free to contact the City Engineer,
Jade Berube, via email at jade.berube@apexenggroup.com, or City Manager, Jonathan Smith at
jsmith@cityofperham.com.