5-10-24 Project Update

May 10, 2024

Even with the rain early this week, construction has continued on Main Street. R.L. Larson’s two construction crews finished the underground water, sewer, and storm sewer on Phase 1. Yesterday, one of the crews shifted to Phase 2, the portion of Main Street from Fourth to Sixth Avenue West. The crew started the sanitary sewer…