2024 Main Street Restoration Project

Final! 10-25-24 Project Update

October 26, 2024

Main Street is Open! With the shorter days and a limited amount of trucks hauling, the paving of the final four blocks of Main Street took a little longer than expected, with the final pavement completed on Tuesday evening by Central Specialties. Following the completion of the paving on Main Street, a temporary surface was…

Asset 1pavingperham

Note: information below is tentative and subject to change at any time during construction process.

Phase #1a

Main Street from 1st Ave S to 5th Ave SW

Business landmarks: Lakes Home Outlet/North Threads to Back in Motion Physical Therapy

Tentative timeline = Phase complete, corners will be completed when phase 1b and phase 4 are in construction.

Phase #2

6th Ave SW to 4th Ave SW 

Business landmarks: Esser's/Perham Police Dept./Perham Fire Dept. to People Ready/Papacitos/Mobil

Tentative timeline: majority of phase complete

Phase #3

Lakeside Drive/Hwy 34/Hwy 51 to 6th Ave SW

Business landmarks: Schmitz Motor Co/Northwoods Life Church to Esser's/Perham Police Dept./Perham Fire Dept.

Combined with Phase #2.

Tentative timeline: majority of phase complete

Phase #4

4th Ave SW through 1st Ave S intersection

Business landmarks: People Ready/United Community Bank to Photo Magic/The Back Porch

Start date: Current - mid-October

Full Depth Reclamation

Main Street/County 80 from Hwy 10 to Hwy 10

Tentative Timeline: outside of downtown core = current, downtown core = will follow Phase #4 completion (mid to end October)