2024 Main Street Restoration Project

6-28-24 Project Update

June 28, 2024

Progress continues along Main Street with activities primarily focused on Phases 2 and 3. On Monday, Knife Lake Concrete arrived in town and has placing concrete all week. Over the course of the week, they have constructed sidewalk and driveways working their way west from Fourth Avenue West toward the intersection of County Highways 34…

Asset 1pavingperham

Note: information below is tentative and subject to change at any time during construction process.

Phase #1a

Main Street from 1st Ave S to 5th Ave SW

Business landmarks: Lakes Home Outlet/North Threads to Back in Motion Physical Therapy

Tentative timeline = Phase complete, corners will be completed when phase 1b and phase 4 are in construction.

Phase #2

6th Ave SW to 4th Ave SW 

Business landmarks: Esser's/Perham Police Dept./Perham Fire Dept. to People Ready/Papacitos/Mobil

Tentative timeline: majority of phase complete

Phase #3

Lakeside Drive/Hwy 34/Hwy 51 to 6th Ave SW

Business landmarks: Schmitz Motor Co/Northwoods Life Church to Esser's/Perham Police Dept./Perham Fire Dept.

Combined with Phase #2.

Tentative timeline: majority of phase complete

Phase #4

4th Ave SW through 1st Ave S intersection

Business landmarks: People Ready/United Community Bank to Photo Magic/The Back Porch

Start date: Current - mid-October

Full Depth Reclamation

Main Street/County 80 from Hwy 10 to Hwy 10

Tentative Timeline: outside of downtown core = current, downtown core = following Phase #4 complete