Project Update 240405 (1) Project Update #2 Construction bids were received for the Main Street Reconstruction project on March 20th and a contract was awarded by the City and County last week. The low bidder and contractor for the project is R.L. Larson Excavating, Inc. of St. Cloud. For those of you that were around…
Note: information below is tentative and subject to change at any time during construction process.
Phase #1a
Main Street from 1st Ave S to 5th Ave SW
Business landmarks: Lakes Home Outlet/North Threads to Back in Motion Physical Therapy
Tentative timeline = Phase complete, corners will be completed when phase 1b and phase 4 are in construction.
Phase #2
6th Ave SW to 4th Ave SW
Business landmarks: Esser's/Perham Police Dept./Perham Fire Dept. to People Ready/Papacitos/Mobil
Tentative timeline: majority of phase complete
Phase #3
Lakeside Drive/Hwy 34/Hwy 51 to 6th Ave SW
Business landmarks: Schmitz Motor Co/Northwoods Life Church to Esser's/Perham Police Dept./Perham Fire Dept.
Combined with Phase #2.
Tentative timeline: majority of phase complete
Phase #4
4th Ave SW through 1st Ave S intersection
Business landmarks: People Ready/United Community Bank to Photo Magic/The Back Porch
Start date: Current - mid-October
Full Depth Reclamation
Main Street/County 80 from Hwy 10 to Hwy 10
Tentative Timeline: outside of downtown core = current, downtown core = following Phase #4 complete