Central Specialties and Ottertail Aggregate have been working on Phases 1, 2 & 3 throughout the week. Early in the week, Central Specialties finished the second lift of pavement on Phases 2 and 3. Ottertail Aggregate worked on all three phases, cutting existing pavement and preparing the subgrade for tie-ins to driveways and parking lots.…
Note: information below is tentative and subject to change at any time during construction process.
Phase #1a
Main Street from 1st Ave S to 5th Ave SW
Business landmarks: Lakes Home Outlet/North Threads to Back in Motion Physical Therapy
Tentative timeline = Phase complete, corners will be completed when phase 1b and phase 4 are in construction.
Phase #2
6th Ave SW to 4th Ave SW
Business landmarks: Esser's/Perham Police Dept./Perham Fire Dept. to People Ready/Papacitos/Mobil
Tentative timeline: majority of phase complete
Phase #3
Lakeside Drive/Hwy 34/Hwy 51 to 6th Ave SW
Business landmarks: Schmitz Motor Co/Northwoods Life Church to Esser's/Perham Police Dept./Perham Fire Dept.
Combined with Phase #2.
Tentative timeline: majority of phase complete
Phase #4
4th Ave SW through 1st Ave S intersection
Business landmarks: People Ready/United Community Bank to Photo Magic/The Back Porch
Start date: Current - mid-October
Full Depth Reclamation
Main Street/County 80 from Hwy 10 to Hwy 10
Tentative Timeline: outside of downtown core = current, downtown core = following Phase #4 complete