2024 Main Street Restoration Project

7-3-24 Project Update

July 7, 2024

With the shortened work week, construction has been limited to a few of the subcontractors on the project. On Monday morning, Central Specialties began the construction of the first course of bituminous pavement on Phases 2 & 3. The two-inch course of pavement was constructed over the course of Monday and Tuesday morning along with…

Asset 1pavingperham

Note: information below is tentative and subject to change at any time during construction process.

Phase #1a

Main Street from 1st Ave S to 5th Ave SW

Business landmarks: Lakes Home Outlet/North Threads to Back in Motion Physical Therapy

Tentative timeline = Phase complete, corners will be completed when phase 1b and phase 4 are in construction.

Phase #2

6th Ave SW to 4th Ave SW 

Business landmarks: Esser's/Perham Police Dept./Perham Fire Dept. to People Ready/Papacitos/Mobil

Tentative timeline: majority of phase complete

Phase #3

Lakeside Drive/Hwy 34/Hwy 51 to 6th Ave SW

Business landmarks: Schmitz Motor Co/Northwoods Life Church to Esser's/Perham Police Dept./Perham Fire Dept.

Combined with Phase #2.

Tentative timeline: majority of phase complete

Phase #4

4th Ave SW through 1st Ave S intersection

Business landmarks: People Ready/United Community Bank to Photo Magic/The Back Porch

Start date: Current - mid-October

Full Depth Reclamation

Main Street/County 80 from Hwy 10 to Hwy 10

Tentative Timeline: outside of downtown core = current, downtown core = following Phase #4 complete