8-30-24 Project Update

By marketing@perhamcc.com | August 31, 2024

Construction crews have been busy over the course of the past week working both on improvements downtown on Phase 4 and on the edges of the City to Highway 10 both on the east and west side of town. Early this week, All States Pavement Recycling completed the initial reclamation of the surface on the…

8-23-24 Project Update

By marketing@perhamcc.com | August 27, 2024

Project Update Various construction crews have been working on multiple portions of Main Street throughout the week, with activities occurring on Phase 4 (First Avenue to Fourth Avenue West) and on the west side of town outside of the City Limits. Early this week, the intersection of Main Street and First Avenue removals occurred, with…

Dreams for Kids Rally & Bingo

By marketing@perhamcc.com | August 21, 2024

19th Annual Rally Sept. 14th, 2024 Fresh Meat & Big Bag Bingo Oct. 12th & Nov. 9th, 2024 Back to Community Events

8-16-24 Project Update

By marketing@perhamcc.com | August 19, 2024

Project Update Main Street construction has started again! On Tuesday, a majority of the new detour redirecting traffic from Main Street west of First Avenue was setup and on Wednesday, removals on Phase 4 began. Ottertail Aggregate has been working on the removals and started west of the intersection of First Avenue to leave the…

8-9-24 Project Update

By marketing@perhamcc.com | August 10, 2024

Over the course of the past two weeks, work has been limited on the Main Street Project. Last week, most construction activities occurred on Seventh Avenue Southeast from Main Street to Third Street South. Construction has been focused on the preparation of the aggregate base for the future roadway that will connect the paved sections…

7-19-24 Project Update

By marketing@perhamcc.com | July 20, 2024

Project cleanup has been the theme over the course of the week after sliding the barricades late last week. Over the course of the week, Ottertail Aggregate has been working on boulevard grading and topsoil placement in Phases 2 and 3, as well as filling in additional aggregate material behind the concrete driveways that were…

7-12-24 Project Update

By marketing@perhamcc.com | July 12, 2024

Central Specialties and Ottertail Aggregate have been working on Phases 1, 2 & 3 throughout the week. Early in the week, Central Specialties finished the second lift of pavement on Phases 2 and 3. Ottertail Aggregate worked on all three phases, cutting existing pavement and preparing the subgrade for tie-ins to driveways and parking lots.…

Turtle Race Park Mural

By marketing@perhamcc.com | July 9, 2024

Turtle Race Park Mural Located in City Hall/Turtle Race Park on the wall of Ottertail Glass, located at 147 East Main Street

Waves of Discovery Mural

By marketing@perhamcc.com | July 9, 2024

Waves of Discovery Mural Located on 1st Ave N on the wall of Photo Magic, located at 102 West Main Street Fun Facts and Hidden Objects This piece was inspired by the artists love for growing up in Perham, the heart of the Minnesota lakes area. It was created with a medium of carved concrete…

Welcome to Perham Mural

By marketing@perhamcc.com | July 9, 2024

Welcome to Perham Mural Located in NP Park on the wall of MN Tru North, located at 200 West Main Street Thank you to our generous supporters: Find these sponsors in the design! PERHAM Find these sponsors in the design! Perham Area Chamber of Commerce & City of Perham – City Hall Building KLN Family…

Scroll To Top