R.L. Larson’s two construction crews continue to work on the underground utility replacement in Phase 1, completing the replacement of the sanitary sewer mains yesterday. On Thursday afternoon, one of the crews also stubbed the sanitary sewer main out of Main Street north on Second Avenue Northeast in advance of Phase 1B, which will occur…
Construction is underway on Main Street and moving quickly. On Monday morning, removals started at the intersection of Third Avenue East and Main Street and worked to the west toward First Avenue. The existing pavement, curb and gutter, trees grates and lights were removed early this week, with completion near the intersection of First Avenue…
Activity has started on Main Street throughout the week as outlined in the last update. Early in the week, some of the signage on Highway 10 directing Truck Traffic away from downtown was setup, with final Traffic Control and Detour signage for the first phase going up on Wednesday. Some of the road closures and…
November 29, 2024 Back to Community Events
Black Friday-Christmas Eve, 2024 Click Here Back to Community Events
October 5, 2024 Click Here Back to Community Events
August 24, 2024 Click Here Back to Community Events
July 25-28, 2024 Facebook Website Back to Community Events
July 12, 2024 Click Here Back to Community Events
A preconstruction meeting was held with various project stakeholders on Tuesday morning. Prime contractor, R.L. Larson Excavating, outlined their preliminary plans for a start date and preliminary schedule for the first phase of construction. Next week, you will begin to see traffic control signage being placed throughout town, in advance of construction scheduled for the…
- « Previous
- 1
- 2
- 3
- 4
- Next »